Progress has been made in the following areas:
§ Concrete footings in Area F (Kitchen) are complete. Underground plumbing has started.
§ The demolition of the back of Beal Gym is being completed.
§ The storm retention system in the student parking lot is ongoing.
§ Area A (New Locker Rooms and Science Classroom wing)excavation completed and ready for pile installation.
§ Ballfields have been stripped of loam. Ledge blasting is starting in this area.
§ Job trailers have arrived and are being setup for occupation.
Over the next couple of weeks the following areas will be addressed:
§ Area F(New Kitchen) foundations and underground plumbing will be completed
§ Pile driving will be continuing for Areas A (New Locker Rooms, classroom wings, administration area and Learning Commons).
§ Work will continue on site utilities and storm retention system in the student parking lot.