Week of July 22, 2012 Construction Update

Progress has been made in the following areas:

§ Concrete footings in Area F (Kitchen) are complete.  Underground plumbing has started.

§ The demolition of the back of Beal Gym is being completed. 

§ The storm retention system in the student parking lot is ongoing.

§ Area A (New Locker Rooms and Science Classroom wing)excavation completed and ready for pile installation.

§ Ballfields have been stripped of loam. Ledge blasting is starting in this area.

§ Job trailers have arrived and are being setup for occupation.

 

Over the next couple of weeks the following areas will be addressed:

§ Area F(New Kitchen) foundations and underground plumbing will be completed

§ Pile driving will be continuing for Areas A (New Locker Rooms, classroom wings, administration area and Learning Commons).

§ Work will continue on site utilities and storm retention system in the student parking lot.