December Project Updates:

The project has really taken shape over the past month.  There are approximately 70-80 workers on site daily.  Sections of the work area are being enclosed to allow for work to continue throughout the winter.  You will also see areas covered by blankets to keep the cold out, one of the challenges of winter work in Maine.  Below are some updates on the work that is currently occuring.

Area F - Over the past month steel erection, exterior sheathing and roofing has been on-going in the Cafeteria, and Lecture Hall areas.  Interior metal stud partition framing, plumbing and HVAC piping are continuing. Windows will begin to be installed over the next few weeks.

October 11, 2012 Construction Update:

 

The practice fields have been built and were seeded during September. Grass is just beginning to grow.

Utilities to the Quarterback Club were reconnected.

Progress is continuing on the High School Construction Project. 

* Blasting is completed and pile driving should be completed as of August 20th. 

* The first coat of paving has been put on the parking lot near Martin Field.  Curbing and the surface coat will be in place by the end of the week of Aug. 20th.  Striping will be completed before students return on September 4th.

Progress has been made in the following areas:

§ Concrete footings in Area F (Kitchen) are complete.  Underground plumbing has started.

§ Stripping of the existing play fields has begun.

§ Phase 1 blasting is almost complete.  